
Fluor Lands EPC Contract for Kentucky Data Center Campus
Fluor has been awarded a definitive engineering, procurement and construction contract for three data center buildings at the Justified Data Campus in Hawesville, Kentucky. The client is TeraWulf, an Easton, Maryland-based data center infrastructure developer, which announced the award in a November 4 release.
Fluor first received a limited notice to proceed in March covering master planning and preconstruction work, and early construction has already begun. State utility regulators approved an electric-service agreement for the roughly $4 billion campus in August. Fluor's expanded scope now includes testing and commissioning.
TeraWulf expects phased ready-for-service completions to begin in late 2027 and run through the second quarter of 2028. The company also secured credit support from Google for debt financing at the campus, where AI company Anthropic holds about $19 billion in contracted lease commitments. TeraWulf's chairman and CEO said the arrangement lets the company scale execution without building a large engineering organization in-house.
Fluor did not disclose the contract value and plans to recognize the award in the fourth quarter once pricing for the first two buildings is final.
For developers and lenders, the deal shows hyperscale-linked campuses moving from preconstruction into execution, with financing tied to investment-grade credit support.
More from Hawesville
More in Kentucky
· Shelbyville, Kentucky
Blue Steel Plans 1.8M SF Steel 64 Industrial Project on 309 Acres in Shelbyville
· Lexington, Kentucky
Newmark Arranges Recapitalization of Lexington’s Fritz Farm Mixed-Use Center
· Lexington, Kentucky
Article Student Living Buys 280-Bed Student Housing Property Near University of Kentucky
· Bowling Green, Kentucky
Gilbane Breaks Ground on $350M Western Kentucky University Student Housing
· Hebron, Kentucky
Midland Atlantic Properties Begins Construction on Hebron, Kentucky Retail Center