Carbon County Approves Conditional Permit for Nuclear-Data Center Campus
Carbon County, Utah, planners approved a conditional use permit for Valar Atomics’ proposed Raceway Energy Campus on 640 acres of state trust land near Wellington. The plan allows for 40 to 120 small modular reactors, but the company cannot begin reactor construction until it receives Nuclear Regulatory Commission licenses. The permit also requires power facilities to be at least half a mile from homes, at least three public town halls and a cleanup bond. One planning commissioner voted against approval at Thursday’s special meeting in Price.
Valar leases 480 acres from the Utah Trust Lands Administration under a 52-year agreement. The lease included a $400,000 signing payment and annual rent of $14,400 during a five-year development period, increasing to $300,000 by year eight. Revenue from the land supports Utah K-12 schools; it previously generated about $4,000 annually.
The permit also includes a natural-gas plant to serve manufacturing, laboratory and data-center buildings before the reactors are built, then provide backup power. The company has separately proposed Project Beehive, a much larger campus on adjacent federal land. Nearly 200 residents attended the meeting, while local petitions seek a temporary pause on large energy projects.
For developers and lenders, the approval is conditional: reactor licensing, infrastructure sequencing and local opposition remain material project risks.