Miami Beach's Lincoln Road Remake Nears Final Phase

Miami Beach’s Lincoln Road Remake Nears Final Phase

Miami Beach, FloridaSource: Miami Today
Infrastructure

Miami Beach expects its Lincoln Road makeover to take roughly two and a half more years. Improvements on Drexel and Meridian avenues are close to finished, and the city is preparing to award a contract for the project's last phase.

According to David Gomez, the city's director of Capital Improvement Projects, the three-phase effort carries a total budget of about $70.9 million, covering design, construction and other costs. The first phase, which focused on lighting upgrades, is complete.

The second phase targets Drexel Avenue between 16th Street and Lincoln Lane North, along with Meridian Avenue between Lincoln Road and 17th Street. Planned work on those blocks includes wider sidewalks. The article cuts off before listing the remaining scope.

For developers, brokers and lenders with exposure to the Lincoln Road corridor, the practical takeaway is a longer construction window and a pending contractor award that could affect access and frontage conditions nearby.