A construction site in Brooklyn where a building collapsed on Wednesday had previously violated a stop-work order from the New York City Department of Buildings, according to the agency. The collapse killed eight people, including two construction workers, and injured eighteen more, Mayor Zohran Mamdani said at a Thursday press conference.

The DOB says it filed a stop-work order and violation on March 20 after inspectors found inadequate overhead protection for neighboring properties in the Flatbush neighborhood during demolition. When inspectors returned on April 23, they found demolition had resumed, which led to a second violation. The agency lifted the order on May 8 after the project team corrected the conditions. It has now issued a new stop-work order citing unsafe operations.

Permit records list Robert Fischman as owner and Cheng-Yi Lin Architecture as architect of record. Neither could be reached for comment. Mamdani said the city is sweeping about 100 sites linked to five main entities involved in the project.

Engineers interviewed noted that deep excavation next to older masonry buildings is common in dense New York construction, and that proper shoring is what protects adjacent structures.

For developers and lenders, the practical takeaway is that shoring compliance and adherence to stop-work orders are under close regulatory scrutiny, and prior violations on a site may draw enforcement attention after an incident.